New Campus Construction Blog
Transition planning
10/15/2009
When embarking on a massive project, such as moving a hospital's operations to a new building, planning starts early.
Work continues inside the new Hospital building
08/27/2009
While the most visible signs of progress on the new Hospital building are the masonry work and window installation, a number of activities are also occurring inside of the building.
Building on schedule to be enclosed by winter
08/14/2009
Construction crews have been making significant progress on the masonry work that began in the spring and still anticipate having the new hospital building enclosed this winter.
A look inside the structure
07/31/2009
As masonry work progresses, crews begin building out interior spaces.
Masonry work making its way around building
07/15/2009
Brick work continues to progress from the west side of the building to the east.
Check out our progress
06/26/2009
New video on our Web site shows you how far we've come in the past year.
Second construction camera now live
06/17/2009
A second construction camera overlooking the construction site is now available on our Web site.
Building enclosure work underway
05/15/2009
Work to enclose the new Elmhurst Memorial Hospital is now underway and the project remains on schedule.
Watch a piece of EMHC history
05/01/2009
A short video clip from the April 16 Topping Off ceremeony for the new Elmhurst Memorial Hospital is now available on our Web site.
Topping off the new hospital
04/16/2009
On the morning of April 16, the new Elmhurst Memorial Hospital building was "topped off" when the final steel beam was placed atop the structure.